Rs 12,976 Crore Order Book: Multibagger Small-Cap Infrastructure Stock Reports Stable Q1 FY27 Profit of Rs 51 Crore
Hindustan Construction Company reported a consolidated net profit of Rs 51.1 crore in Q1 FY27, while maintaining a strong order book of Rs 12,976 crore and emerging as the lowest bidder for projects worth Rs 2,124 crore
✨ Key Takeaways
On Thursday, Indian equity benchmark indices traded marginally higher, with the benchmark Nifty 50 index gaining 11.35 points, or 0.05 per cent, to 24,636.00. Amid the positive market sentiment, Hindustan Construction Company (HCC) share price declined 1.64 per cent to Rs 21.55 after the company announced its Q1 FY27 financial results.
HCC Q1 FY27 Financial Performance
On a consolidated basis, HCC reported revenue of Rs 993.4 crore in Q1 FY27 compared with Rs 1,091.3 crore in the corresponding quarter of the previous year, resulting in a 9.0 per cent YoY decline. Consolidated net profit increased marginally to Rs 51.1 crore from Rs 50.7 crore, registering a 0.7 per cent YoY growth.
Order Inflow and Order Book
Looking for Future-Ready Growth Opportunities?
Explore DSIJ’s Vriddhi Growth - a research-driven service focused on identifying innovative, fast-growing companies adapting to technological change and long-term market trends.
Download Service BrochureDuring the quarter, HCC secured a new order worth approximately Rs 125 crore. The company also emerged as the lowest bidder (L1) for projects valued at approximately Rs 2,124 crore, of which HCC's share is around Rs 1,671 crore. Additionally, bids worth approximately Rs 9,997 crore remain under evaluation.
The company reported a work-on-hand (order book) of Rs 12,976 crore as of June 30, 2026, compared with Rs 12,971 crore as of March 31, 2026, providing healthy revenue visibility.
Project Execution Updates
HCC achieved breakthrough of Head Race Tunnel (HRT) Faces 2 and 3 for the 520 MW Tapovan Vishnugad Hydroelectric Project during the quarter. At the 1,000 MW Vishnugad Pipalkoti Hydroelectric Project, the company handed over the Machine Hall for Units 1 and 2, while HRT excavation reached 85 per cent completion. Earthworks and steel liner fabrication also progressed at the Bhivpuri Pumped Storage Project.
Also Read - Stock Below Rs 40: This Small-Cap Steel Stock Completes 1 MW Captive Solar Power Project; Check Details
In the transportation segment, tunnel boring machine (TBM) deployment commenced at the Indore Metro project, while construction activities advanced at the Patna Metro and Agardanda Creek Bridge projects. In the industrial segment, Hindalco's Aditya Aluminium Smelter expansion project received approval for the first pot shell prototype, enabling bulk fabrication. The company also continued execution of the Fast Reactor Fuel Cycle Facility after completing deliveries for Rajasthan Atomic Power Project Units 7 and 8.
About HCC
Hindustan Construction Company Limited is one of India's leading infrastructure companies with an engineering legacy of 100 years. The company has constructed 26 per cent of India's hydropower generation capacity, 60 per cent of its nuclear power generation capacity, over 4,036 lane kilometres of expressways and highways, more than 402 km of complex tunnelling, and 403 bridges.