KNR Constructions order book and mining ramp-up strengthen growth visibility

KNR Constructions Ltd.

Broker Recommendation:

ACCUMULATE

Broker: Prabhudas Lilladher

17 Nov 2026

Sector: Infrastructure

Original PDF
Reco. Price

₹107

CMP

₹106.91

Target

₹121

Upside

13.08%

Investment View and Valuation

Prabhudas Lilladher’s November 17, 2026 report upgrades KNR Constructions to ACCUMULATE from HOLD and revises the target price to Rs 121 from Rs 126. The broker considers the risk-reward more favourable after the stock declined about 20 per cent over three months and its valuation corrected.

The target valuation applies 10 times 1HFY29E price-to-earnings to KNR’s EPC business and book value to its BOT and HAM investments.

Valuation component Value per share
EPC business Rs 75
BOT and HAM projects Rs 46
Total target price Rs 121

Q2FY27 Operating Performance

KNR reported muted Q2FY27 operating performance. Revenue was Rs 477 crore, down 3 per cent YoY and broadly in line with Prabhudas Lilladher’s and consensus expectations. Road and irrigation execution remained subdued, HAM project commencement was delayed and mining contributed little in H1FY27.

Metric Q2FY27 Change / comparison
Revenue Rs 477 crore Down 3 per cent YoY
EBITDA Rs 43.9 crore Down 18 per cent YoY; 15 per cent below the broker’s estimate
EBITDA margin 9.2 per cent Down from 10.9 per cent a year earlier
Reported PAT Rs 280.8 crore Included an exceptional gain of Rs 292.5 crore from the sale of a HAM asset
Adjusted PAT Rs 30 crore Up 7.5 per cent YoY, aided by other income of Rs 14.7 crore

Margin pressure reflected elevated input costs amid inflation and currency fluctuations, higher employee costs and lower equipment utilisation.

Vriddhi_Growth.webp

Participating in Future Growth Themes

Structural changes and innovation can create long-term investment opportunities. DSIJ's Vriddhi Growth focuses on businesses positioned around emerging trends and scalable growth opportunities.

Order Book and Revenue Visibility

The central positive for the broker is a substantially stronger order book. FY27-to-date order inflow was Rs 8,000 crore, including Rs 1,400 crore received after Q2FY27. This took the order book to Rs 16,400 crore, compared with Rs 8,700 crore at FY26-end.

Mining represents 42 per cent of the order book and roads 43 per cent, improving revenue visibility and business diversification. Management targets additional H2FY27 order inflows of Rs 4,000 crore to Rs 5,000 crore, with the Gevra mine and sizeable highway HAM projects as opportunities. KNR held projects worth around Rs 400 crore at the L1 stage.

Management Guidance and Broker Estimates

Management retained standalone FY27 revenue guidance of Rs 2,200 crore to Rs 2,300 crore and expects revenue above Rs 3,000 crore in FY28. It expects EBITDA margin to remain near the Q2FY27 level in H2FY27 because of input costs, overheads and equipment utilisation, with recovery from FY28 as HAM and mining projects ramp up. Management did not commit to a 13 per cent margin target.

Metric FY27 guidance / estimate FY28 estimate FY29 estimate
Revenue Guidance: Rs 2,200–2,300 crore Rs 2,624.5 crore Rs 3,378.6 crore
EBITDA margin Near Q2FY27 level in H2FY27 11 per cent 11 per cent
Estimate revision — Revenue raised 4.5 per cent; EPS cut 8.3 per cent Revenue raised 1.5 per cent; EPS cut 7.6 per cent

Mining MDO Growth Opportunity

Mining MDO is KNR’s prospective next growth engine. The Kusmunda coal mining project has an executable order value of Rs 3,300 crore and is to be fully executed by KNR.

  • Management targets mining revenue of Rs 100 crore in H2FY27.
  • It expects Rs 400 crore from Kusmunda and Rs 300 crore from Banhardih in FY28, subject to project commencement.
  • Banhardih operations are expected in four to five months, subject to land availability.
  • Cumulative mine capex is estimated at around Rs 1,000 crore.
  • Mining margins are expected near 5 per cent after royalty.

Capital Allocation, Receivables and Key Risks

KNR has monetised all four HAM assets to Indus Infra Trust, although Rs 425 crore remains withheld. Irrigation receivables were Rs 660 crore, HAM receivables were Rs 330 crore and total receivables, including unbilled revenue, were about Rs 1,400 crore. Management expects about Rs 600 crore of Telangana irrigation payments by December 2026.

Existing and new HAM projects require further equity commitments of about Rs 710 crore, alongside mining capex.

The operating and funding outlook could weaken because of delayed project commencement, land availability constraints, weak execution, elevated costs, lower equipment utilisation and slower receivable collections.

Download Original Research Report

Disclaimer: This is a summary of a research report published by the broker/research house identified above. The views, recommendations, target prices and estimates are those of the respective broker and do not represent DSIJ investment advice. The summary may be AI-assisted, hence please refer to the original report for complete details, disclosures and risks.